Riot’s $28 billion AI lease lets Anthropic block voluntary cuts
Riot Platforms’ lease with Anthropic became binding Nov. 4 and requires the AI company’s consent for voluntary cuts to its 910-megawatt Corsicana load. Mandatory grid orders are exempt.
Riot Platforms’ lease with AI company Anthropic became binding Nov. 4 after the companies signed it Oct. 28. The agreement requires Anthropic’s consent before Riot can voluntarily reduce the power load assigned to Anthropic’s facilities at Riot’s Corsicana, Texas, site or enroll the premises in voluntary demand-response programs.
Orders from the utility or grid operator that require a power reduction are exempt. The approval requirement applies to Anthropic’s leased load, not to Riot’s entire Bitcoin-mining operation.
The lease covers 910 megawatts of planned critical IT capacity. Riot expects to deliver an initial block on June 28, 2027, complete the first 400-megawatt phase by September 2027, deliver another 200 megawatts in January 2028 and provide the final 310 megawatts by July 2028.
Base rent will begin at $130 per kilowatt of delivered critical IT capacity per month and increase 3% annually. Rent will start separately for each pad. Anthropic can receive an extension of up to 60 days if its equipment is not installed when capacity is delivered. After rent begins, payments are described as independent of facility utilization.
Riot’s earnings presentation estimates about $28 billion in revenue during the initial lease term, including annual rent increases and before the amortization of tenant reimbursements. The figure represents expected revenue over the future lease period, not cash already received or current profit.
Riot will build the site and maintain its power infrastructure. Anthropic will pay the electricity bill and cover taxes, insurance and other site expenses. Riot estimates about $5.5 billion in hard construction costs, including site work and reimbursements for tenant equipment.
Riot must reimburse Anthropic for eligible module costs of up to $4 million per megawatt of achieved critical IT capacity. The reimbursement is subject to financing on terms reasonably acceptable to Riot. If financing is unavailable after commercially reasonable efforts, Riot can provide rent credits instead. The credits cover the reimbursement and 12% annual interest over the remaining initial lease term, reducing the rent Riot receives in cash.
If a capacity block is delayed by more than 60 days, Riot must provide escalating rent credits capped at 270 days of base rent for the affected undelivered capacity. A phase delayed beyond 270 days may be terminated on 30 days’ notice, subject to cure rights and extensions for force majeure or delays caused by Anthropic.
Riot previously reduced electricity use at its Rockdale and Corsicana sites during periods of high demand and sold unused or uneconomic contracted power. The company reported $25 million in companywide power-curtailment credits in the third quarter. It also receives transmission savings in later years when it reduces electricity use during peak-demand periods.
The Corsicana lease does not quantify any curtailment income Riot might forgo because Anthropic must approve voluntary reductions to its load.