AI firms seek Bitcoin miners’ power as contracts shape returns

AI companies are seeking Bitcoin miners’ grid connections for data centers, but conversions require new cooling, networking and construction. Contracts determine how revenue is shared.

Bitcoin miners spent years securing electricity, land, substations and grid connections. AI companies are now seeking those assets for data centers, but mining sites require major upgrades before they can support artificial-intelligence workloads.

Mining facilities run application-specific integrated circuits, or ASICs, that can be switched off when power prices change. AI data centers require densely packed computing equipment, liquid cooling, high-speed networking, backup power and stricter uptime standards.

A grid connection therefore provides a starting point rather than a completed data center. CoinShares estimated in September that converting mining infrastructure for AI costs about $8 million to $15 million per megawatt, compared with $700,000 to $1 million per megawatt for conventional mining infrastructure.

Mining equipment has also lost value as competition increased and mining revenue weakened. Core Scientific recorded a $266.5 million write-down of mining equipment and infrastructure in the first quarter. The charge included $151.6 million for mining machines and $114.9 million for mining infrastructure. The company’s AI hosting business had a positive gross margin, while its mining operation was losing money at the gross-profit level.

Core Scientific’s agreements with AI cloud provider CoreWeave show how data-center revenue is divided. Core Scientific reported $136.7 million in colocation revenue for the second quarter of 2026. By mid-July, 437 megawatts were serving customers that were being billed. License fees accounted for $98.8 million, while $35.1 million came from electricity charges passed through to customers. The electricity reimbursement appears as revenue and as an equivalent expense, so it does not increase gross profit.

Under agreements disclosed in April, CoreWeave generally pays a base license fee starting at $100 per kilowatt per month, with annual increases of 3.5%. CoreWeave also funds or reimburses certain construction costs. For specified equipment owned by Core Scientific, CoreWeave can receive credits of up to $1.5 million per megawatt against future base fees.

At the initial rate, one megawatt produces a monthly base fee of $100,000. A 50% construction credit would reduce the payment to $50,000 until the credit is used. A full $1.5 million credit would take about 30 months to recover at that payment level, before rent increases and other contract terms.

Core Scientific remains responsible for completing and financing the facilities. Its agreements provide daily credits of $20,000 or $30,000 in specified late-delivery situations. Some delays can give CoreWeave the right to terminate an order.

Core Scientific recorded $954.2 million in capital expenditure during the first half of 2026, including $180.9 million funded by CoreWeave. In May, a financing subsidiary issued $3.3 billion of secured notes carrying a 7.75% interest rate. The full principal would produce about $255.8 million in annual interest before repayments.

Other miners are pursuing different AI strategies. SWI Group took control of Genesis Digital Assets earlier in 2026 and announced an €800 million capital increase on Oct. 12 to expand its AI infrastructure business. On Oct. 26, SWI Compute disclosed about $1 billion in orders for NVIDIA equipment and announced its first customers, with some contracts still being finalized.

Genesis reported in June that its properties had more than 1.3 gigawatts of energized and approved connections across 15 facilities. SWI later reported about 1.2 gigawatts of secured grid connections. The disclosures did not provide a site-by-site breakdown of capacity already usable for AI or capacity requiring additional work. SWI has not disclosed which Genesis sites will host its NVIDIA systems or when those facilities may begin producing AI revenue.

Approved capacity, electricity already flowing to a site and a place in a grid-connection queue represent different stages of development. In Texas, regulators approved ERCOT’s Batch Zero review process in June. The state also ordered an audit of about 474 gigawatts of proposed large-load connections.

The cost of construction, financing terms, equipment ownership, customer payments and usable power capacity will determine how much revenue reaches site owners and shareholders.